Construction underway on new Sydney Light Rail stop

News Date: 17 Jul 2017

Category: Railways

NSW Premier Gladys Berejiklian has given an update on the progress of the Sydney Light Rail project, revealing that more than a third of the track installed and that construction is now underway on the first of 19 light rail stops from the City to the south east.

“At the start of the year we had 500 metres of track in the ground. As of today we have more than 8000 metres, which is more than a third of the track now in place,” Ms Berejiklian said.

“It is great to see that we have finished installing more than one kilometre of track on Alison Road at Randwick and that work is now underway at the Wansey Road light rail stop which will be the first one completed in the next couple of months.”

Track installation in the Randwick area is an important first step towards the testing and commissioning of the light rail system.

“We are also seeing progress in the CBD, with cars returning to part of George Street near Circular Quay where track has been installed including paving laid between the rails,” Ms Berejiklian said.

Each light rail vehicle will be able to carry up to 450 people, equivalent to up to nine standard buses. With up to 15 light rail vehicles an hour operating in each direction on opening, this gives a capacity of 13,500 passengers per hour. This will mean less congestion on Sydney’s roads and more reliable travel times.

The Premier said: “This demonstrates the NSW Government’s commitment to delivering important transport infrastructure on time and on budget.”

Sydney Light Rail will provide high frequency ‘turn up and go’ transport services from Circular Quay to Randwick and Kingsford from 2019.

More Industry & Project News

Major milestone reached on Pacific Highway upgrade

Another major milestone has been reached on the Pacific Highway upgrade after 14km of new, divided highway was opened to traffic between Kempsey to Kundabung.


New Jingi Jingi Creek bridge complete

Road safety and flood immunity on the Warrego Highway has been improved following the completion of a new bridge over Jingi Jingi Creek.


Tender awarded for early Gladstone Hospital works

Paynter Dixon Pty Ltd has been awarded the $1.6 million tender for early works on the new $42 million Gladstone Hospital Emergency Department.


Gartside Street upgrade underway

The Gartside Street upgrade that will deliver streetscape improvements to make the street safer through better separation of vehicles and people has recently gotten underway.


Construction on new Colac Police Station begins

Construction is underway on the new Colac Police Station thanks to the Victorian State Government's investment in regional policing.